New Engineering maintenance pits for Norwood bus garage

  
  

At Arriva London, we are always looking at ways of developing better methods of serving our customers and helping our staff to do their jobs more effectively. A most important part of this is to ensure that all our buses are fully serviceable and ready to go out on the route.

Preparing the site
Preparing the site

As part of our continuous improvement programme, investment has been made in our engineering facilities right across our seventeen garages. The programme started with the vehicle maintenance pit upgrade in Tottenham and Stamford Hill garages in North London, and has now extended to our garages in the South at Brixton and Norwood.

Off loading the prefabricated pit units
Off loading the prefabricated pit units

The upgrade has been carried out over several months as it is a major upheaval for the garages while day-to-day operations carry on. The work involves removing the old concrete pits and replacing them with steel pre-fabricated versions. The pits are deeper than the older versions, which were installed when the garages were built over fifty years ago, and were designed for the higher floor, step access buses of the time.

Working round the construction work
Working round the construction work

Apart from providing more space to work, the new pits are better illuminated and with the steel side walls painted gloss white, give much better reflective surfaces that are also far easier to maintain. They have also been extended to accommodate the increased length of the New Routemasters buses.

The transition has meant that the garages have had to share their servicing work with other Arriva London Engineering facilities.

Ready for use
Ready for use

As Norwood Engineering manager Micky Letts explains: -

The new pits in action
The new pits in action

“The transition has run really smoothly and none of the routes served by the garage have been affected by the change. We had a lot of noise and disruption during the pit refurbishment but boy was it worth every minute. The refurbishment has given us a much cleaner and better environment to work in for all staff, and it brings a smile to my face when I arrive for work each morning and walk into the new workshop area.”

If you are a PSV technician and would like to work for Arriva London, then please visit our recruitment page.

  
  

Tags:   News
Published : Thu 3rd Nov. 2016
All archived articles
Published : Tue 23rd Feb. 2010 - Wed 3rd Mar. 2010
 
Arriva London supporting South London Storm
Arriva London is pleased to announce a new community partnership with rugby league club South London Storm.
Norwood Garage Centenary
11th March 2009 was an important date in the history of Norwood garage, it being the day the site celebrated its 100th birthday.
Arriva London's ladies Race for Life
Arriva London’s ladies will be in the pink again this year raising more money for charity and getting in a little gentle exercise at the same time.
New Route for Arriva London
It’s been busy, busy, busy at Barking garage as Arriva London prepares to take over the operation of route 325 on Saturday 6th March.
The Arriva Heritage Fleet
Our historic red Routemasters, and our special gold RM 6, are available for hire, whatever your requirements
Special treat for Billy
Fifteen-year-old bus enthusiast Billy Birkett, from Dagenham, was given the present of a lifetime thanks to the team at Arriva London’s Clapton garage.
 

Please wait...

 

.Delivered by CSN MCL / All content copyright © 2007 - 2018 original copyright holders, except where individually stated. All rights reserved. E&OE.